Boise Paper Mill Final Energy Audit Report
Summary
Investment: $31,000
Payback Period: 1 month
Annual Cost Savings: $1 million
Energy Savings: 154,000 MmBtu per year
Dow Chemical Company Petrochemical Plant Final Energy Audit Report
Summary
Investment: $225,000
Payback Period: 1.5 months
Annual Cost Savings: $1.9 million
Energy Savings: 272,000 MmBtu per year
OS Longman State Department Agriculture Food Supply Final Energy Audit Report
Summary
Investment: $12,472
Payback Period: 6 months
Annual Cost Savings: $24,102
Energy Savings: 6,026 GJ per year
Wascana Powerhouse Final Energy Audit Report
Summary
Investment: $29,959*
Payback Period: 1.93 years
Annual Cost Savings: $15,518
Energy Savings: 7,218 GJ per year
*Additional costs to remove asbestos not part of this quote.
AV Nackawic Inc Pulp And Wood Manufacturing Facility Final Audit Report
Summary
Investment: $265,676
Payback Period: 2.6 years
Annual Cost Savings: $102,043
Energy Savings: 14,390,131.2 Btu per day
Goodyear Tire Production Plant Final Energy Audit Report
Summary
Investment: $180,000
Payback Period: 2.5 months
Annual Cost Savings: $875,000
Energy Savings: 93,000 MMBtu per day and 224,000 gallons per year of No. 6 fuel oil
Leduc Food Processing Development Center Final Energy Audit Report
Summary
Investment: $176,000
Payback Period: 7 months
Annual Cost Savings: $10,100
Energy Savings: 2,527 GJ
West Linn Paper Manufacturing Mill Final Energy Audit Report
Summary
Investment: $7,529
Payback Period: 6 months
Annual Cost Savings: $379,000
Energy Savings: 58,200 MMBtu per day
Cairnsmore Place Healthcare Facility Final Energy Audit Report
Summary
Investment: $ 3,150
Payback Period: 1.67 years
Annual Cost Savings: $1,888
Energy Savings: 128 GJ per year